← Collection02 — Moss Landing BESS
02 / Power & EnergyMoss Landing, California · 2022–2023
Moss
Landing.
Battery Energy Storage / California
Selected Projects · 02 / 16
WORKS ATLAS / 02
Moss Landing BESSMoss Landing, California / 2022–2023
01 — The Project
Grid-scale energy storage at the intersection of generation, transmission, and the energy transition.
The Moss Landing Battery Energy Storage System is a major grid-scale storage facility. The technical portfolio identifies a 750 MW / 3,000 MWh program.
Field safety support encompassed construction activities around transformers, switchgear, grounding, control houses and protection equipment.
ProjectMoss Landing BESS
LocationMoss Landing, California
Assignment2022–2023
Field affiliationField safety / electrical construction
03 — Professional Contribution
A contribution within
a larger effort.
- 01
Construction safety
Supported safety meetings, investigations, and compliance audits during the storage-system expansion.
- 02
Electrical equipment interfaces
Monitored field safety around transformers, switchgear, grounding, control houses, and protection equipment.
- 03
Field documentation
Documented findings and corrective follow-up in Intelex.
The scale is architectural.
The work is human.
Major infrastructure takes shape through many disciplines, shared responsibilities, and the work of field teams.
Moss Landing BESS / California